連日(ri)來,冶建(jian)公司第五分公司一項目為(wei)確保(bao)工程如期交付,項目部緊(jin)盯目標節點(dian),科學組織施工,多措并舉加快(kuai)項目建(jian)設進度(du)。
項目現場
為高效推進(jin)施工,項(xiang)目部結合“大干二季度(du) 沖刺半年(nian)紅”主題勞(lao)動競(jing)賽,制(zhi)(zhi)定科學的施(shi)工(gong)(gong)方案,倒排(pai)(pai)工(gong)(gong)期、全(quan)力推進(jin)。每周(zhou)組(zu)織各班組(zu)召開進(jin)度(du)協(xie)調(diao)會,實時跟(gen)蹤進(jin)度(du)落實情況,及時解決現(xian)場問(wen)題。同時,建立獎罰(fa)激勵機制(zhi)(zhi),充分(fen)調(diao)動施(shi)工(gong)(gong)積極性。此外,項(xiang)目部還(huan)強化(hua)(hua)現(xian)場監督,優化(hua)(hua)施(shi)工(gong)(gong)組(zu)織,合理安排(pai)(pai)交叉作業(ye),全(quan)面(mian)掀(xian)起趕工(gong)(gong)熱(re)潮(chao),在保障安全(quan)與質量的前提下加(jia)快施(shi)工(gong)(gong)進(jin)度(du)。
下一步,第五(wu)分公(gong)(gong)司(si)和項(xiang)目部將(jiang)緊盯目標任務,嚴抓安全生產、質(zhi)量管理等工(gong)作,高(gao)效推(tui)進項(xiang)目建設(she),全力推(tui)動公(gong)(gong)司(si)業績實現恢(hui)復性增長。
(圖文/第五分(fen)公(gong)司 韋艷萍(ping))